Vail's new high speed gondola is moving right along. The lower gondola terminal is almost complete and the mid-Vail terminal building is enclosed. Earlier this summer a Huey Helicopter helped pour concrete bases for the new gondola lift towers that were inaccessible by road. Towers 19, 17, 8 were poured on day one and 9 & 4 on day two.  Vail Resorts has said they are on schedule to open on 11/17. 